Dates | Task | Team Work | Notes |
---|---|---|---|
4/07/2024 - 17/07/2024 | Market research and competitor analysis | 1-competitor analysis | Focus on identifying gaps and opportunities in existing apps |
18/07/2024 - 31/07/2024 | Defining requirements and key features | 2- requirements App-Features | Prioritize must-have features for MVP |
1/08/2024 - 14/08/2024 | Project planning and timeline setup | Create detailed milestones and deliverables |
Dates | Task | Team Work | Notes |
---|---|---|---|
15/08/2024 - 21/08/2024 | Analyze and define database requirements | Identify data entities and relationships | |
22/08/2024 - 28/08/2024 | Design ER diagrams | Visual representation of database structure | |
29/08/2024 - 4/09/2024 | Normalize database schema | Ensure minimal redundancy | |
5/09/2024 - 11/09/2024 | Define database tables and fields | Create SQL scripts for table creation | |
12/09/2024 - 18/09/2024 | Design and implement indexes | Optimize query performance | |
19/09/2024 - 25/09/2024 | Setup database backups and recovery | Ensure data integrity and recovery |
Dates | Task | Team Work | Notes |
---|---|---|---|
26/09/2024 - 2/10/2024 | Identify core use cases | List and prioritize use cases | |
3/10/2024 - 9/10/2024 | Detail use case descriptions | Write detailed use case scenarios | |
10/10/2024 - 16/10/2024 | Create use case diagrams | Visual representation of use cases | |
17/10/2024 - 23/10/2024 | Review and validate use cases | Get feedback from stakeholders |
Dates | Task | Team Work | Notes |
---|---|---|---|
24/10/2024 - 30/10/2024 | Setup development environment and repository | Set up CI/CD pipelines for efficiency | |
31/10/2024 - 6/11/2024 | Build basic project structure | Follow best practices for scalability |
Dates | Task | Team Work | Notes |
---|---|---|---|
7/11/2024 - 10/11/2024 | User Authentication - Presentation Layer | Develop UI for login and registration | |
7/11/2024 | Develop login screen | ||
8/11/2024 | Develop registration screen | ||
9/11/2024 | Develop password reset screen | ||
11/11/2024 - 14/11/2024 | User Authentication - Domain Layer | Implement business logic for authentication | |
11/11/2024 | Implement login logic | ||
12/11/2024 | Implement registration logic | ||
13/11/2024 | Implement password reset logic | ||
15/11/2024 - 19/11/2024 | User Authentication - Data Layer | Integrate with Firebase and other providers | |
15/11/2024 | Integrate Firebase Auth for email/password | ||
16/11/2024 | Integrate Google authentication | ||
17/11/2024 | Integrate Apple authentication | ||
18/11/2024 | Integrate Microsoft authentication | ||
19/11/2024 | Implement Two-Factor Authentication | Enhance security with two-factor authentication |
Dates | Task | Team Work | Notes |
---|---|---|---|
20/11/2024 - 26/11/2024 | Task Management - Presentation Layer | Develop UI for task list and details | |
20/11/2024 | Develop task list screen | ||
21/11/2024 | Develop task details screen | ||
22/11/2024 | Develop task addition/editing screen | ||
27/11/2024 - 3/12/2024 | Task Management - Domain Layer | Implement business logic for tasks | |
27/11/2024 | Implement create task logic | ||
28/11/2024 | Implement read task logic | ||
29/11/2024 | Implement update task logic | ||
30/11/2024 | Implement delete task logic | ||
1/12/2024 | Implement task prioritization | ||
2/12/2024 | Implement task categorization | ||
3/12/2024 | Implement subtask management | ||
4/12/2024 - 10/12/2024 | Task Management - Data Layer | Integrate with Firebase for task data | |
4/12/2024 | Integrate Firebase Firestore for tasks | ||
5/12/2024 | Implement task due dates and reminders | ||
6/12/2024 | Implement task status tracking | ||
7/12/2024 | Implement task filters and sorting | ||
8/12/2024 | Implement bulk actions for tasks | ||
9/12/2024 - 10/12/2024 | Test and validate task management features |
Dates | Task | Team Work | Notes |
---|---|---|---|
11/12/2024 - 14/12/2024 | Dashboard - Presentation Layer | Develop UI for Dashboard | |
11/12/2024 | Develop main Dashboard screen | ||
12/12/2024 | Add key metrics and visualizations | ||
15/12/2024 - 17/12/2024 | Dashboard - Domain Layer | Implement business logic for Dashboard | |
15/12/2024 | Implement data aggregation logic | ||
18/12/2024 - 21/12/2024 | Dashboard - Data Layer | Integrate with Firebase for Dashboard data | |
18/12/2024 | Fetch and display user-specific metrics | ||
20/12/2024 - 21/12/2024 | Test and validate Dashboard features |
Dates | Task | Team Work | Notes |
---|---|---|---|
22/12/2024 - 27/12/2024 | Implement data synchronization with Firebase | Ensure real-time data updates | |
22/12/2024 | Setup real-time data sync | ||
23/12/2024 | Handle sync conflicts | ||
24/12/2024 - 27/12/2024 | Test and validate data synchronization |
Dates | Task | Team Work | Notes |
---|---|---|---|
28/12/2024 - 31/12/2024 | Implement task sharing feature | Ensure secure sharing options | |
28/12/2024 | Setup sharing permissions | ||
29/12/2024 | Develop sharing UI | ||
30/12/2024 - 31/12/2024 | Test and validate task sharing |
Dates | Task | Team Work | Notes |
---|---|---|---|
1/01/2025 - 5/01/2025 | Implement offline functionality and sync | Test thoroughly for offline use cases | |
01/01/2025 | Setup local storage | ||
02/01/2025 | Handle offline data sync | ||
3/01/2025 - 5/01/2025 | Test and validate offline functionality |
Dates | Task | Team Work | Notes |
---|---|---|---|
6/01/2025 - 12/01/2025 | Integrate with Google Calendar and Outlook | Test integration with multiple accounts | |
06/01/2025 | Setup calendar API integration | ||
07/01/2025 | Develop calendar sync UI | ||
8/01/2025 - 12/01/2025 | Test and validate calendar integration |
Dates | Task | Team Work | Notes |
---|---|---|---|
13/01/2025 - 17/01/2025 | Handle notifications and alerts | Push notifications for task reminders | |
13/01/2025 | Setup push notification service | ||
14/01/2025 | Develop in-app notification UI | ||
15/01/2025 | Implement email notifications | ||
16/01/2025 - 17/01/2025 | Test and validate notifications |
Dates | Task | Team Work | Notes |
---|---|---|---|
18/01/2025 - 24/01/2025 | Writing unit tests | Cover all critical functions | |
25/01/2025 - 31/01/2025 | Conducting integration tests | Ensure all modules work together | |
1/02/2025 - 7/02/2025 | Full system testing | Test end-to-end scenarios |
Dates | Task | Team Work | Notes |
---|---|---|---|
8/02/2025 - 14/02/2025 | Preparing and launching the final version | Ensure a smooth launch process | |
15/02/2025 - 21/02/2025 | Preparing documentation and user guide | Make it user-friendly and comprehensive | |
22/02/2025 - 28/02/2025 | Monitoring performance and collecting feedback | Track key performance metrics | |
1/03/2025 - 7/03/2025 | Implementing improvements and fixes | Prioritize critical issues |